2023 Annual Park Paving Project
Our annual park paving project is happening at various parks in February and May (all dates are subject to change without notice). Various parks will have pavement repairs and seal coating to improve your park user experience. During repairs, the park section, trailhead, or trail section will be closed for safety with no detours. Closures will be messaged through signage at the site, on social media and in our newsletter.
Schedule (subject to change)
Centennial Trail - Lake Cassidy Trailhead to Getchell Trailhead
Centennial Trail - Hwy. 92 Trailhead
Feb. 8: Asphalt, Sign and Striping (complete)
Flowing Lake Park Campground and Entrance Road (day-use area not affected)
Feb. 10: Curbing (complete) Feb. 13: Asphalt (complete) - March 13: Curb revisions, speed hump, new asphalt
- May 1-2: Sealcoat
Interurban Trail - Pedestrian Bridge (near 124th and McCollum Park)
Kayak Point Campground Loop
Kayak Point Park Day-Use Area
Feb. 6: Asphalt (complete) - March 13: Crack sealing of patch edges
Gissberg Twin Lakes Park - South Parking Lot
Feb. 6: Crack Fill, Asphalt and Striping (complete) - March 10: Crack fill and sealing edges of patch and restriping
Wenberg County Park Boat Launch
- May 8-9: Sealcoat and Striping
Whitehorse Trail - Cicero Segment
Feb. 10: Bollards (complete) March 2: Root barrier installation (complete) - May 4-5: Sealcoat
Whitehorse Trail - Miller Shingle Trailhead
Feb. 8: Asphalt (complete) - May 3-4: Sealcoat, ADA Signs, Striping and Wheel Stops
Whitehorse Trail - SR 530 Slide Memorial Trail Segment
March 2: Paving (complete)- May 8-9: Sealcoat