2023 Annual Park Paving Project
Our annual park paving project is happening at various parks in February and May (all dates are subject to change without notice). Various parks will have pavement repairs and seal coating to improve your park user experience. During repairs, the park section, trailhead, or trail section will be closed for safety with no detours. Closures will be messaged through signage at the site, on social media and in our newsletter.
Schedule (subject to change)
Centennial Trail - Lake Cassidy Trailhead to Getchell Trailhead
- Feb. 14-17: Crack Fill and all Asphalt/Root Barrier
- Feb. 20-24: Crack Fill and all Asphalt/Root Barrier
Centennial Trail - Hwy. 92 Trailhead
- Feb. 8: Asphalt, Sign and Striping
Flowing Lake Park Campground and Entrance Road (day-use area not affected)
- Feb. 10: Curbing
- Feb. 13: Asphalt
- May 1-2: Sealcoat
Interurban Trail - Pedestrian Bridge (near 124th and McCollum Park)
Kayak Point Campground Loop
Kayak Point Park Day-Use Area
Gissberg Twin Lakes Park - South Parking Lot
- Feb. 6: Crack Fill, Asphalt and Striping
Wenberg County Park Boat Launch
- May 8-9: Sealcoat and Striping
Whitehorse Trail - Cicero Segment
- Feb. 10: Bollards
- May 4-5: Sealcoat
Whitehorse Trail - Miller Shingle Trailhead
- Feb. 8: Asphalt
- May 3-4: Sealcoat, ADA Signs, Striping and Wheel Stops
Whitehorse Trail - SR 530 Slide Memorial Segment