Fencing will be installed on two sides of the perimeter of the north field at Martha Lake Airport Community Park to prevent further vehicle trespass. Work is to be completed by Commercial Fence Cooperation.
3/29/2019 - Install Project Construction Sign
4/10/2019 - Site visit, schedule utility locates, layout fence line and location of cores
4/15/2019 - Begin core drilling and digging fence post holes
4/15/2019 - 4/19/2019 - Set fence posts, clean up spoils form post hole digging
4/22/2019 - 4/26/2019 - Install frame for fence
4/29/2019 - 5/1/2019 - Stretch and tie fence fabric to frame
5/2/2019 - 5/3/2019 - Install fence protection on top line of fence & demobilize
For questions on the project, please contact:
1. Dave McConnell - Associate Park Planner, Snohomish County Parks and Recreation Department at (425) 388-6627 or by email at david.mcconnell@snoco.org
2. Eric Duke, Project Manager, Commercial Fence Corporation at (206) 767-7433 or by email at eduke@fenceitall.com