Snohomish County replaced a culvert under Soundview Dr NW, in the Warm Beach area. The pre-existing culvert was deemed a fish-passage barrier. The new box culvert is designed to meet fish passage standards. This project connects Lake Martha Creek to a small Port Susan estuary that the Tulalip Tribes restored in 2019. Stream channel restoration was also completed. The project increases fish access to upstream habitat.
Construction began in August and finish in September of 2022
This project required a full 24/7 road closure during construction (see map).
The estimated cost for this culvert replacement was about $500,000 and was funded by Surface Water Utility funds.
Engineer III
Ph: 425-262-2672
3000 Rockefeller Ave., M/S 303
Everett, WA 98201
Email Surface Water Management Division
Ph: 425-388-3464
Project #RR48661
Construction schedules are subject to change based on many factors that include: public safety; availability of funding, staffing, equipment and materials; right of way issues; permitting requirements; coordination with utilities and other agencies; soil conditions under roadway and seasonal changes.