Project Description
Phase 2 is the addition of 12 non-utility campsites (with shared water) and shower equipped restrooms at Whitehorse Park campground. Construction is scheduled for June 2022 with an estimated completion date of August/September 2022. Most work will be performed weekdays between the hours of 8am-5pm. Existing (Phase 1) campsites will remain open during construction, but may be impacted by noise and equipment traffic.
Current Status
Updated 6/6/22
- Contractor will mobilize to the site the week of 6/6/2022
- First iteration of construction will be the 12 tent camping sites with a duration of approximately 6 weeks. This work will include:
- Felling approx. 70 trees and clearing the underbrush for the tent loop and 12 sites
- Excavation for the water lines
- Grading and rocking the loop for car travel
- Pouring the concrete foundation and pad for restroom
- Second iteration will be the construction of the restroom building.
- The work for this building depends on the delivery of the restroom package. This is anticipated for mid to late August
- The restroom will be constructed in 90 days