240th Street SE Railroad Crossing Improvements

May 2019 Update

The second weekend closure has been scheduled to begin at 7 p.m., Friday May 10. A small portion of 240th St SE will be closed at the railroad intersection, east of Snohomish-Woodinville Rd. The road will reopen by 5 a.m. Monday, May 13. See more closure details below.

Construction Schedule

Construction will begin on April 27 and is expected to last about three months. Crews will be working from 7 a.m. to 5 p.m., Monday through Friday and during full closures outlined below. During normal construction hours, 240th St SE at the railroad intersection will remain open but some delays may occur.


Full Weekend Closures

This project requires three full weekend closures of a small portion of 240th St SE at the railroad intersection, east of Snohomish-Woodinville Rd. During the full weekend closures there will be no access through the intersection on 240th St SE. Motorists will need to use alternate routes. Snohomish-Woodinville Rd and the entrance to Costco will remain open to traffic.

Full Overnight Closures

This project may require up to eight full overnight closures of 240th St SE at the railroad intersection. These would take place Monday through Thursday from 7 p.m. to 5 a.m. If these closures are needed, the dates will be announced at a later time. Sign up to receive project updates to be notified of closures.

January 2019 Update

McCann Construction has been awarded the contract for this project. Construction is expected to take place in spring 2019 and last approximately six weeks. The project will require some full weekend and overnight closures on 240th St SE, east of the Snohomish-Woodinville Rd intersection. More information regarding closures and the construction schedule will be available in March 2019.

March 2018 Update

Snohomish County Public Works received a grant for $417,620 from the Federal Rail Crossing Safety Program. This project will be advertised for bids in fall 2018 and construction is expected in 2019.

May 2017 Update

Improvements to the 240th Street SE Railroad crossing, east of Snohomish Woodinville Road, will not be constructed this year as originally planned. Bids received from contractors were significantly higher than the funds available for this project. Snohomish County Public Works is currently evaluating maintenance options at the intersection and additional funding alternatives. More information will be provided as it becomes available.

Description

Snohomish County Public Works had proposed improvements to the railroad crossing at 240th St SE, east of Snohomish Woodinville Road. Construction would include updates to the roadway from Snohomish Woodinville Road to the rail crossing, installation of a reinforced crossing, the addition of a connection to the existing sidewalk on the north side of the road, and upgrades to pedestrian facilities.

Funding

Snohomish County Public Works received a grant from the Washington State Freight Rail Assistance Program.

Environmental Review

A Notice of Land Disturbing Activity Permit was issued on December 11, 2016 with a 21-day comment period. The comment period ended January 3, 2017. The notice is available by viewing the link below: