The county's work on this project is completed however the trail is not open at this time.
For more information on the trail, visit the Parks & Recreation webpage
Snohomish County Public Works is restoring approximately 1-mile of the Whitehorse Trail along State Route 530 near milepost 36.9 to C-Post Road. In addition to the trail, the county will replace two culverts in the area.
For more information on the trail, visit the Parks & Recreation webpage.
Construction is scheduled to begin in July 2016 and should be complete by mid-October 2016. Work is expected to occur Monday through Thursday, depending on weather and holidays. Construction is being completed by Taylor’s Excavators, Inc.
The reconstruction of the trail is expected to cost approximately $980,000 and is funded by the Federal Emergency Management Agency (FEMA) and the Snohomish County Parks & Recreation Department.
View additional road information.
Project #RR9354
Construction schedules are subject to change based on many factors that include: public safety; availability of funding, staffing, equipment and materials; right of way issues; permitting requirements; coordination with utilities and other agencies; soil conditions under roadway and seasonal changes.