Whitehorse Trail Restoration (Arlington)

The county's work on this project is completed however the trail is not open at this time.

For more information on the trail, visit the Parks & Recreation webpage


Description - Completed

Snohomish County Public Works is restoring approximately 1-mile of the Whitehorse Trail along State Route 530 near milepost 36.9 to C-Post Road. In addition to the trail, the county will replace two culverts in the area.


For more information on the trail, visit the Parks & Recreation webpage.


Schedule

Construction is scheduled to begin in July 2016 and should be complete by mid-October 2016. Work is expected to occur Monday through Thursday, depending on weather and holidays. Construction is being completed by Taylor’s Excavators, Inc.


Funding

The reconstruction of the trail is expected to cost approximately $980,000 and is funded by the Federal Emergency Management Agency (FEMA) and the Snohomish County Parks & Recreation Department.