Description
This was a Public Works Surface Water Management Division project to replace a damaged culvert under Maple Road. Road Maintenance Division staff did the work to retain the safety and structural integrity of the road and increase water flow capacity. The new culvert is an upgrade from 12 inches in diameter to 30 inches.
The project site is located south of 180th Street SE, east of Broadway Avenue, and west of Waverly Drive in the Cathcart/Clearview area of the Snohomish County.
Construction Impacts
A full road closure of two weeks was needed to excavate and replace the damaged culvert. The road was closed to all through traffic for two weeks during the spring/summer of 2014.